Question: The waterfall project development process is well-suited for instances where: a. Requirements are allowed to float throughout the duration of the project b. Customer needs
The waterfall project development process is well-suited for instances where:
| a. | Requirements are allowed to float throughout the duration of the project | |
| b. | Customer needs change quickly | |
| c. | Time constraints exist | |
| d. | Budget constraints exist |
2)
The sprint portion of the Agile Project Management process is targeted to last:
| a. | 10 plus or minus 2 weeks | |
| b. | 7plus or minus 1.5 weeks | |
| c. | 5 plus or minus 1.5 weeks | |
| d. | 2.5 plus or minus 1.5 weeks |
3)
The customers articulate the necessary features of a software project through:
| a. | stories | |
| b. | tasks | |
| c. | requests for proposal | |
| d. | bid rigging |
4)
Which of these numerical (quantity) comparisons is CORRECT?
| a. | Scrum meeting >Sprint | |
| b. | Scrum master > Development team | |
| c. | Sprint time box >Project duration | |
| d. | Daily scrum duration < Development work duration |