Question: The WBS includes only deliverables that are really needed; deliverables not in the WBS are not part of the project. This statement is:Single choice.(1 Point)

The WBS includes only deliverables that are really needed; deliverables not in the WBS are not part of the project. This statement is:Single choice.(1 Point)

True.

False.