Question: The work breakdown structure control points for the management of a project are the: a ) Activities b ) Milestones c ) Constraints d )

The work breakdown structure "control points" for the management of a project are
the:
a) Activities
b) Milestones
c) Constraints
d) Work packages
 The work breakdown structure "control points" for the management of a