Question: The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally validated through the WBS ? Communications
The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally validated through the WBS
Communications plans
Requirements Traceability Matrix
Schedule and cost
RACI chart