Question: The Work Breakdown Structure should be decomposed to a level that identifies individual work packages for ____________. Group of answer choices The level of detail
The Work Breakdown Structure should be decomposed to a level that identifies individual work packages for ____________. Group of answer choices The level of detail specified by the sponsor Each specific deliverable listed in the project scope document Each person that planned the project Each resource assigned to the project