Question: The workday is seven hours long. The demand for completed product is 750 per day. Balance the line using sequential restrictions and the longest-operating-time rule.

The workday is seven hours long. The demand for

The workday is seven hours long. The demand for completed product is 750 per day.

Balance the line using sequential restrictions and the longest-operating-time rule.

What is the efficiency of the line balanced?

The following tasks are to be performed on an assembly line: TASK TASKS THAT MUST PRECEDE 6 I SECONDS 20 7 20 22 15 10 16 8 E F A B B D EF G IG The workday is seven hours long. The demand for completed product is 750 per day