Question: There are 1 2 Agile Principles to guide the implementation of Agile Project Management ( APM ) . Which of the following is not one

There are 12 Agile Principles to guide the implementation of Agile Project Management (APM). Which of the following is not one of those 12 principles?
Group of answer choices
Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.
Deliver working software frequently, from a couple of weeks to a couple of months.
Business people and developers must work together daily throughout the project.
Define all of the requirements up-front so that changes are minimized later in the process.