Question: There are 1 4 different activities for the given project. What is this project's critical path? table [ [ Activity , Duration ( months

There are 14 different activities for the given project. What is this project's critical path?
\table[[Activity,Duration (months),\table[[Predecessor],[5]],Successors],[A,2,-,D, E],[B,4,+,F, G],[c,3,+,G],[D,1,A,H],[E,5,A,H.I],[F,3,B,J],[G,4,B,C,K],[H,5,D,E,L],[1,4,E,L],[J,3,F,L],[K,2,G,M.N],[L,1,H, I,,-],[M,3,K,+],[N,4,K,4]]
BGKM
BGKN
AEHL
CGKM
There are 1 4 different activities for the given