Question: There are 2 questions which use the same data shown below: The manufacturing facility has the following workstations which take the indicated amount of time
There are 2 questions which use the same data shown below:
The manufacturing facility has the following workstations which take the indicated amount of time to process materials before moving the WIP on to the next workstation.
| Workstation # | Workstation Processing Time (minutes) |
| 1 | 20 |
| 2 | 3 |
| 3 | 18 |
| 4 | 19 |
| 5 | 1 |
If production starts at 8:00 AM, at what time will the first product be completed?
| 9:10am | ||
| 10:01am | ||
| 9:01am | ||
| 8:50am |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts