There are 3 source and 4 destinations, For the data below, construct an initial feasible solution. Cost
Fantastic news! We've Found the answer you've been seeking!
Question:
There are 3 source and 4 destinations, For the data below, construct an initial feasible solution.
Cost | Destination 1 | Destination 2 | Destination 3 | Destination 4 | Supply |
Source 1 | 12 | 18 | 9 | 11 | 105 |
Source 2 | 19 | 7 | 30 | 15 | 14 |
Source 3 | 8 | 10 | 14 | 16 | 50 |
Demand | 80 | 60 | 70 | 90 | 300/300 |