Question: There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y- E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 25

There are five critical paths in a network.

There are five critical paths in a network. A-B-C-D-X-E, A-F-U-Y-E, A-F-G-Y- E, A-H-J-K-L-E and A-S-T-Y-E. Each activity in this network can be crashed by 25 hours. The maximum possible reduction in the project duration will be: a. 125 hours b. 350 hours Cc. 100 hours Cd. Insufficient information Ce. 175 hour