Question: There are four activities on the critical path, and the standard deviations for their durations are 5, 12, 34, and 16 days. The standard deviation

There are four activities on the critical path, and the standard deviations for their durations are 5, 12, 34, and 16 days. The standard deviation of the duration of the critical path is:

a. 67

b. 16.75

c. 8.185

d. 1581

e. 39.76

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!