Question: There are four critical paths in a network. A-B-C-D- E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum
There are four critical paths in a network. A-B-C-D- E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 3 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $580, E is $595 and all other activities is : $145 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1450 per week, E is $1740 per week and for all other activities is $290 per activity per week. You have a maximum crashing budget of $3630. The maximum possible reduction in the project duration will be: O a. 3 weeks O b. 2 week O c. 6 weeks O d. 4 weeks O e. 5 weeks