Question: There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 6 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $440, E is $455 and all other activities is : $110 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1100 per week, E is $1320 per week and for all other activities is $220 per activity per week. You have a maximum crashing budget of $2755. The maximum possible reduction in the project duration will be:
a.5 weeks
b.4 weeks
c.6 weeks
d.2 week
e.3 weeks