There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. They process a single product.
Question:
There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. They process a single product. The flow of the accepted and rejected products are shown in the process flow chart.
The total volume of production is 115 products per hour. 19 % of the products of Station-1 need repair and are directed to Station-3 for repair, the rest are sent to Station-2. 15 % of the products of Station-2 need repair and are directed to Station-3 for repair, the rest are sent to Station-4. 10 % of the incoming products of Station-3 are rejected, are sold at a low price, and leave the process. The rest go to Station-4. All the products of Station-4 are good, no need to repair, and no rejection. On average, there are 33 products in Station-3.
What percentage of the products are rejected. Enter your answer as PERCENTAGE with ONE DECIMAL point.