Question: There are many specific terms utilized in the Material Requirements Planning process. Which of the following best differentiates between the terms Gross Requirements and Net

There are many specific terms utilized in the Material Requirements Planning process. Which of the following best differentiates between the terms Gross Requirements and Net Requirements from an MRP Planning perspective?
A. the gross MRP may not be computerized, but the net requirements plan must be computerized.
B. the gross MRP does not take taxes into account, whereas the net requirements plan includes the tax considerations.
C. the net requirements plan includes consideration of the inventory on hand, whereas the gross MRP does not.
D. the gross MRP includes consideration of the inventory on hand, whereas the net requirements plan does not.
 There are many specific terms utilized in the Material Requirements Planning

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!