Question: There are several documents that should be updated during the monitoring and control phase. One of these documents is the _ _ _ _ _

There are several documents that should be updated during the monitoring and control phase. One of these documents is the _________.
a.
Project procurement plan
b.
Alternation log
c.
Risk and complications log
d.
Communications log