Question: There are three paths on a network diagram. The duration of path ACF is 21 days. The duration of path ADGH is 23 days. The
There are three paths on a network diagram. The duration of path ACF is 21 days. The duration of path ADGH is 23 days. The duration of path BEH is 19 days. Below is the information to make a crashing decision.
| Activity | Max. days of crashing | Crashing cost per day |
| A | 1 | 2350 |
| B | 3 | 800 |
| C | 3 | 1800 |
| D | 2 | 2575 |
| E | 2 | 2050 |
| F | 1 | 1600 |
| G | 4 | 2200 |
| H | 2 | 2450 |
Given the above information, the first activity's to be crashed is [A] (simply show an activity alphabet) for [B] day(s) (simply show a number. if you believe you can crash multiple time for the first activity, please show total. ) with a cost of [C] (simply show a number) per day.
Answer For A-
Answer For B-
Answer For C-
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts