Question: There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station

There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station 2, finally to station 3 , and then leave the process. There are 2 resources in Station 1, 3 resources in Station 2, and 3 resources in Station 3. The TOTAL capacity of these stations (including all the recourses of that station) per hour are 14,18 , and 15 , respectively. Compute the THEORETICAL flow time. 45 minutes. 37.14 minutes. 47 minutes. 30.57 minutes. 35 minutes