Question: There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station
There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station 2, finally to station 3, and then leave the process. There are 3 resources in Station 1, 3 resources in Station 2, and 3 resources in Station 3. The TOTAL capacity of these stations (including all the recourses of that station) per hour are 24, 24, and 9. The last 3 numbers are the TOTAL capacity of the stations, respectively. Compute the THEORETICAL flow time.
Group of answer choices
37 minutes.
35 minutes.
31.07 minutes.
43.57 minutes.
50 minutes.