Question: There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station
There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station 2, finally to station 3, and then leave the process. There are 4 resources in Station 1, 3 resources in Station 2, and 4 resources in Station 3. The HOURLY capacity of EACH SINGLE RESOURCE in these resource pools is 20 , 15 , and 20, respectively. The last 3 numbers are the capacity of a single machine in each of the three stations, respectively. Compute the THEORETICAL flow time.
Group of answer choices 13 minutes. 14 minutes. 10 minutes. 16 minutes. 12 minutes.