Question: There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station
There are three sequential operations (Station 1, Satiation 2, and Station 3) in a process. Incoming applications go to station 1 first, then to Station 2, finally to station 3, and then leave the process. There are 2 resources in Station 1, 3 resources in Station 2, and 3 resources in Station 3. The TOTAL capacity of these stations (including all the recourses of that station) per hour are 14, 18, and 15, respectively. Compute the THEORETICAL flow time.
45 minutes.
37.14 minutes.
47 minutes.
30.57 minutes.
35 minutes.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts