Question: There are usually changes to cost in a project. When they are approved, what process do they fall into: a. Cost management b. Estimate costs
There are usually changes to cost in a project. When they are approved, what process do they fall into:
a. Cost management
b. Estimate costs
c. Control costs
d. Plan costs