Question: There is a 95.05% chance the project below can be completed in X days or less. What is X? In the space provided below type
There is a 95.05% chance the project below can be completed in X days or less. What is X? In the space provided below type in the values for each activitys expected time, variance, list of critical activities, Project duration and value of X. Draw the network diagram (diagram required only in the pdf file). Activity ----- Predecessors----------- Optimistic (days)----------- Most likely (days) ------------pessimistic(days) ------A ------------none ---------------------------1 --------------------------------4 --------------------------------------- 7 ------B------------none ----------------------------2 --------------------------------2 --------------------------------------- 2 ------C---------------A-------------------------------2 --------------------------------5 --------------------------------------- 8 ------D---------------A-------------------------------3 --------------------------------4 --------------------------------------- 5 ------E--------------B,C -----------------------------4 --------------------------------6 --------------------------------------- 8 ------F--------------B,C------------------------------0---------------------------------0 --------------------------------------- 6 ------G--------------D,E -----------------------------3 --------------------------------6 --------------------------------------- 9
1. Expected value for each activity: BLANK-1
2. Variance for each activity: BLANK-2
3. Critical activities: BLANK-3
4. Project duration: BLANK-4
5. X = BLANK-5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts