Question: There is a network given below. The numbers in parenthesis show the completion time of each task. Write the integer mathematical model in an open

There is a network given below. The numbers in

There is a network given below. The numbers in parenthesis show the completion time of each task. Write the integer mathematical model in an open form that calculates the total completion time of the project (15 points). What is the completion time of this project (5 points)? D(2) 2. 7 E(1) A(2) J(5) K(5) F(3) B(3) 8 1 6 C(4) H(2) G(1) 3 5