Question: There is a process using 4 resources: A, B, C and D. The process flow diagram is shown below, along with the capacities for

There is a process using 4 resources: A, B, C and D.

  

There is a process using 4 resources: A, B, C and D. The process flow diagram is shown below, along with the capacities for each of the resources: A B (15 units/min) C D (15 units/min) (60 units/min) (80 units/min) D (20 units/min) (a) What is the bottleneck of the process, and what is the process capacity? (3 points) (b) What is the cycle time of the process? (2 points) (c) What is the flow time of the process, i.e., assuming there is no waiting time in the buffers? (3 points) Activ Go to