Question: There is an inverse relationship between task durations and direct resource cost: to reduce the duration of a task, there must be an increase in

There is an inverse relationship between task durations and direct resource cost: to reduce the duration of a task, there must be an increase in the direct resource costs associated with that task. There is a limit to this approach, however; this relationship only holds until a point is reached at which additional resources would have no impact on reducing task duration. This minimum duration is known as ______. A. normal point B. normal limit C. crash limit D. crash point