Question: There is only one output to the Plan Risk Management process. Which of the following is this output? Group of answer choices Risk Management Plan

There is only one output to the Plan Risk Management process. Which of the following is this output?
Group of answer choices
Risk Management Plan
Risk Register
Risk Related Contractual Agreements
Organizational Process Assets Updates