Question: These are input data for CPM analysis: Activities Predecessors Time in weeks A - 5 B A 7 C A 8 D B,C 9 E
These are input data for CPM analysis:
| Activities | Predecessors | Time in weeks |
| A | - | 5 |
| B | A | 7 |
| C | A | 8 |
| D | B,C | 9 |
| E | B | 2 |
| F | D,E | 10 |
Identify its Critical Path and available slack times for all activities. Provide as Word or Excel file a full CPM diagram with ES, EF, LS, LF numbers as it is described in the video.
Your answer may look like:
Sketch of diagram,
Critical Path is - ABEF,
Slack times: C - 4; D - 3
EXCEL STATS... i know its pretty tedious. would appreciate the help
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts