Question: They are two systems, A&B. Estimated profit for System A is $0.65 per unit and for System B is $0.45 per unit. You seek to
They are two systems, A&B. Estimated profit for System A is $0.65 per unit and for System B is $0.45 per unit. You seek to maximize total profit.3 However, to manufacture these systems at your company, you'll need to compete for internal resources. To manufacture a single unit of System A requires 4.0 minutes of machining, 1.0 minutes at a soldering station, and 2.0 minutes for final software testing. System B requires 2.4 minutes of machining and 6 minutes of software testing. Capacity of the machining department is 1,100 minutes per week, capacity of the soldering station is 600 minutes per week, and capacity of final software testing is 1,500 minutes per week.
What is the constrained linear program.
How many units of System A and B should you produce, and what is the total profit.