Question: They need your help in developing the Distribution Requirement Plan (DRP) for one of their more popular items. Please use the information below to develop
They need your help in developing the Distribution Requirement Plan (DRP) for one of their more popular items. Please use the information below to develop the DRP schedule. (Show your work)
Item: URT-8254
Order Policy: 125
Lead Time: 1 week
No Pent up Demand
|
| April | May | ||||||
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Quantity on-hand (beginning inventory) | 0 |
|
|
|
|
|
|
|
| Forecast | 1,000 | 1,200 | 1,150 | 1,250 | 1,300 | 1,200 | 1,250 | 1,200 |
| Projected on-hand inventory (ending inventory) | (1,000) |
|
|
|
|
|
|
|
| MRP planned receipts (arrival) | 0 |
|
|
|
|
|
|
|
| MRP planned order releases (order) | 0 |
|
|
|
|
|
|
|
Please give step by step instructions and show work