Question: This assignment will be graded on a 20-point scale. co mment An activity-on-node diagram is shown below. Times are in weeks. 6 NTI a compuesto

This assignment will be graded on a 20-point

This assignment will be graded on a 20-point scale. co mment An activity-on-node diagram is shown below. Times are in weeks. 6 NTI a compuesto se a) Compute the ES, EF, LS, and LF for each activity. The format is ne To EF LS LF b) Compute the slack for each activity. c) What is the project duration? How do you know? d) What is the critical path? How do you know