Question: This exercise contains only parts b, c, and d. Part 2 b) Activities on the critical path for the project are ________ Part 3 The

 This exercise contains only parts b, c, and d. Part 2

This exercise contains only parts b, c, and d.

Part 2

b) Activities on the critical path for the project are

________

Part 3

The total project completion time is

________days. (Round your response to two decimal places.)

Part 4

c) For the given project, the earliest start (ES) and earliest finish (EF) are:

(Round your responses to two decimal places.)

Activity

ES

EF

A

Part 5

B

Part 6

C

Part 7

D

Part 8

E

Part 9

F

Part 10

G

Part 11

H

Part 12

I

Part 13

J

Part 14

K

Part 15

For the given project, the latest start (LS) and latest finish (LF) are:

(Round your responses to two decimal places.)

Activity

LS

LF

K

Part 16

J

Part 17

I

Part 18

H

Part 19

G

Part 20

F

Part 21

E

Part 22

D

Part 23

C

Part 24

B

Part 25

A

Part 26

d) Referring to the standard normal table, the probability that Kelle Carpet and Trim will finish the project in

43

days or less is

________

(Enter as a probability and round your response to two decimal places.)

This exercise contains only parts b,c, and d. b) Activities on the critical path for the project are AGIKCDEGIKBEGIKAFHKBEFHKCDEFHKCJ

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!