Question: This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train

This exercise only contains parts b, c, d, e, and f.
b) Given the demand, the cycle time for the production of the new train set?
seconds (round your response to one decimal place).
c) The theoretical minimum number of workstations?
(round your response up to the next whole number).
e) The total idle time per cycle for the process?
seconds (enter your response as a whole number).
f) The efficiency of the assembly line with 5 workstations?
(enter your response as a percentage rounded to one decimal place).
If one used 6 workstations instead of 5, the efficiency of the assembly line would be?
(enter your response as a percentage rounded to one decimal place).

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts