Question: This Gantt chart can be used to show: activity E can begin as soon as activity A is complete. activities D and B can be

This Gantt chart can be used to show:
activity E can begin as soon as activity A is complete.
activities D and B can be done simultaneously.
activity D must come before activity C.
activity F can be done at the same time as D.