Question: ( This information applies to questions 9 - 1 0 ) In a bicycle factory, frames are delivered to an assembly station 5 at a

(This information applies to questions 9-10) In a bicycle factory, frames are delivered to an assembly station 5 at a time. It takes 15 minutes for frames to be manufactured and delivered to assembly. The assembly station produces 32 bicycles each hour and management has decided that the salety stock should be 4 units. Demand during the lead time is:
12
480
8
4
16
 (This information applies to questions 9-10) In a bicycle factory, frames