This information should be used for questions 4-6. The Borer Company has a contract for a trenchless
Question:
This information should be used for questions 4-6. The Borer Company has a contract for a trenchless pipe-laying project which has four tasks as the major segments. Completion is allocated to each portion according to its direct cost, and output is the measure of progress for each portion.
Allocation of Completion
Task | Estimated Cost ($) | Total Quantity | Quantity to Date | Allocated Completion |
---|---|---|---|---|
1 | 30,000 | 3,000 CY | 3,000 CY | 0.1 |
2 | 50,000 | 1,000 CY | 800 CY | 0.3 |
3 | 15,000 | 25,000 SF | 10,000 SF | 0.15 |
4 | 85,000 | 2,000 CY | 1,500 CY | 0.45 |
180,000 | 1.00 |
Calculate the percentage of completion, presenting it as a ratio (i.e. 0.XX, accurate to 2 decimal places, rounding if necessary).
5.
The cost summary is shown in the table below.
Contract Amount = $360,000
Total Estimated Cost of Revenue | To Date | To Finish |
---|---|---|
Direct Cost | $150,000 | $120,000 |
Project Overhead | $20,000 | $10,000 |
Calculate the total estimated gross profit.
6.
Use the effort expended method and calculate the revenue earned to date with Alternative B.
Advanced Financial Accounting
ISBN: 978-0078025624
10th edition
Authors: Theodore E. Christensen, David M. Cottrell, Richard E. Baker