Question: This is a 3 part question. QUESTION 2 Bandit Manufacturing The following May information is available for Bandit Manufacturing Company when it produced 4,500 units:
QUESTION 2 Bandit Manufacturing The following May information is available for Bandit Manufacturing Company when it produced 4,500 units: Standard: Material Labor 2 pounds per unit @ $5.80 per pound 2.5 direct labor hours per unit@$10.00 per hour Actual: Material Labor 9,900 pounds purchased and used @$5.65 per pound 12,375 direct labor hours at $9.75 per hour Refer to Bandit Manufacturing. What is the material price variance? oa.$1,485 U b.$1,485 F C. $637.50 F d. $637.50 U