Question: This is a first half question. Crash the following project. You will receive $125 for each time period that the project is reduced. The paths

This is a first half question. Crash the
This is a first half question. Crash the following project. You will receive $125 for each time period that the project is reduced. The paths are given below. Indicate the sequence in which tasks are crashed, the most economic duration of the project, and the amount of money saved by crashing. Activity Normal Time Minimum Time Crash Cost 10 7 $100 B 12 9 $50 C 10 8 $60 D 8 6 $150 6 m 4 $75 7 4 $20 The paths are: ACE BCE BDE BDF