For an activityonnode network such as that presented in the textbook, which of the following is true regarding each activity that is on the critical path?
Select one or more:
a the activity's slack is zero
b the activity's early finish equals the activity's late finish
c the activity's late start equals the activity's late finish
d the activity's early start equals the activity's late start
e the activity's early start equals the activity's early finish
f the activity's late start equals the activity's early finish
g the activity's early start equals the activity's late finish
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock