3 The following network diagram for a project is illustrated below (the numbers in parentheses represent activity's duration in days): 1. Identify the project critical path ? (1 p) 2. What will happen to project completion time if activity E delays 3 days in the project? (1 p) 3. Caiculate the total float for activity C. (1 P)