Question: This is all the info there is.... to answer the questions...what do you mean durations ? A set of activities and their times (in days)
| This is all the info there is.... to answer the questions...what do you mean "durations" ? A set of activities and their times (in days) are provided for a project along with their dependencies. The times are a=optimistic, b=pessimistic, and m=most likely. | ||||
| ACTIVITY | a | m | b | Immediate Predecessor(s) |
| A | 4.2 | 8.4 | 11.2 | - |
| B | 2.8 | 5.6 | 5.6 | - |
| C | 1.4 | 2.8 | 4.2 | - |
| D | 8.4 | 9.8 | 11.2 | C |
| E | 2.8 | 5.6 | 8.4 | B,D |
| F | 8.4 | 14 | 19.6 | A,E |
| G | 1.4 | 2.8 | 5.6 | A,E |
| H | 4.2 | 8.4 | 12.6 | F |
| I | 14 | 15.4 | 16.8 | G |
| J | 19.6 | 22.4 | 28 | C |
| K | 2.8 | 11.2 | 14 | H,I |
| Calculate the Expected Times of Completion for each activity. | ||||
| What is the Expected Time of Completion and the standard deviation of the project (based on AON diagram using critical path (CPM))? | ||||
| Calculate Slack1 and Slack 2 for all activities of the project. | ||||
| What is the probability of completing the project in 55 days? | ||||
| Prepare a complete Gannt Chart for the project showing activities (based on time of completion for each and dependencies) and slack. |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock