Question: This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the
This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between! The details of the project activities are as follows - The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 1