Question: This is an Integrated Production System question! Please answer STEP BY STEP ( NO EXCEL PLEASE) 1. Today is the last day of January, and
This is an Integrated Production System question! Please answer STEP BY STEP ( NO EXCEL PLEASE)
1. Today is the last day of January, and a backpack company is planning its
production and workforce levels for the next four months. Backpack sales are seasonal and
the sales forecasts are as follows:
Month. Production days Demand forecast
February 20 12200
March 23 17600
April 22 14000
May 20 6300
Currently, the company has 86 workers on the payroll. Historical records show that during a
period of 26 working days when there were 100 workers on the payroll, the company
produced 12,000 backpacks. The cost to hire a new worker is $125 and the cost of firing a
worker is $300. Holding costs are $0.75 per case per month. Currently, there are 4500
backpacks in stock and in each month the company desires to hold an extra 1000 backpacks
each month as a buffer. It would also like to start May with 3000 backpacks on hand.
Find the zero inventory plan (apart from the 1000 backpacks reserved in each month) for
the company over the next four months. Suppose no stock-out is allowed and inventory can
be carried to future periods to satisfy demands in those periods.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts