THIS IS BASIC LEVEL NO COMPLICATIONS, JUST BE ACCURATE WITH THE SAME NUMBERS AS GIVIN.
Answer questions 1 to 7 based on the following information:

Medro and Mariana have just finished carrying out the CPM method on their south east Asia project as shown below. Answer the questions based on the table and network diagram. The times are in units of days.

The earliest time to start G is:
a. day 10
b. day 25
c. day 27
d. day 35
2
The latest time to finish B is:
a. day 0
b. day 4
c. day 3
d. day 7
3
The cost to complete the project in normal time is:
a. not enough information to answer the question
b. 1180 KD
c. 1750 KD
d. 570 KD
4
The length of the path B-D-G-J is:
a. cannot be determined
b. 65 days
c. 44 days
d. 109 days
5
The critical path is:
a. C-E-H
b. B-E-I
c. C-E-I
d. A-D-G-J
6
If F is to be delayed by 7 days, will the project be delayed?
a. No
b. Yes
c. Not enough information to answer the question
7
The slack of H is:
a. 12 days
b. 10 days
c. 25 days
d. 37 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!