Question: This is for QSO 420 project management. I need help making a chart that captures the SPI, CPI, and CR for the software customization, technical

This is for QSO 420 project management. I need help making a chart that captures the SPI, CPI, and CR for the software customization, technical infrastructure, and combined.

Software Customization May June July Aug Sep Oct
SPI 111.04% 105.85% 109.18% 109.95% 113.20% 106.04%
CPI 111.97% 107.92% 116.83% 115.95% 118.82% 118.82%
CR 1.24 1.14 1.28 1.27 1.35 1.26
Technical Infrastructure
SPI 100.00% 92.95% 91.87% 93.82% 94.37% 88.40%
CPI 100.00% 86.57% 87.86% 87.83% 91.74% 91.74%
CR 1.00 0.80 0.81 0.82 0.87 0.81
Combined Projects
SPI 105.52% 99.40% 100.52% 101.89% 103.79% 97.22%
CPI 105.96% 96.76% 101.53% 101.05% 104.76% 104.76%
CR 1.12 0.96 1.02 1.03 1.09 1.02

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!