Question: This is multiple choice question. Several levels of decision makers add certain percentages as safety margins. The executive level of the organization just completed a

This is multiple choice question. Several levels of decision makers add certain percentages as safety margins. The executive level of the organization just completed a retreat for critical chain management and were energized and much wiser in the ways of project management. As they know that everyone has been routinely adding certain percentages as safety margins, they want to scale the project back to an unpadded estimate. How much should the top management cut?

team's decision

10%

project manager's decision

30%

divisional manager's decision

10%

a.41%

b.36%

c.none of these

d.31%

e.26%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!