Question: This is the answer for a plz explain 1. a. SOT rule: D C A B 1 D B 12 Time (days) Job Lateness A
This is the answer for a plz explain
1. a. SOT rule: D C A B 1 D B 12 Time (days) Job Lateness A 6-5 B 12 - 9 3 C 3-7 CA D 1 - 10 Average lateness = -9/4 = -2.25 days Note: The fact that the average is negative simply means that, on average, jobs were early. Some, however, were lateStep by Step Solution