Question: This is the ONLY Project Cost Management activity that is NOT performed during the Planning Process. Estimate Costs Control Costs Plan Cost Management Determine Budget
This is the ONLY "Project Cost Management" activity that is NOT performed during the "Planning Process."
Estimate Costs
Control Costs
Plan Cost Management
Determine Budget
Control Budget
Determine Costs
Control Estimates