Question: This is the only question I need to be answered/explained: Calculating Project NPV: In the previous problem, suppose the required return on the project is
This is the only question I need to be answered/explained: Calculating Project NPV: In the previous problem, suppose the required return on the project is 12 percent. What is the projects NPV? ( I know the answer is NPV $128,787.07 ) But, can you show me the steps on how to solve it?
Previous problem answer
| Cash flows: | |||
| Annual sales | $1,735,000.00 | ||
| Less: Annual cost | $650,000.00 | ||
| Less: Dep | 2,320,000/3 | $773,333.30 | |
| Before tax Income | $311,666.70 | ||
| Less: Tax 21% | $65,450.00 | ||
| After Tax | $246,216.70 | ||
| Add: Dep | $773,333.30 | ||
| OFC | $1,019,550.00 | ||
Also, the original question for this one was....
Calculating Project OCF [LO1] Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.32 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which time it will be worthless. The project is estimated to generate $1.735 million in annual sales, with costs of $650,000. If the tax rate is 21 percent, what is the OCF for this project?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
